| Robot and application fit |
Payload, reach, tool weight, cycle time, workspace, and required positioning performance. |
Robot model datasheet; documented payload and reach calculations; application layout; cycle-time estimate; end-effector and workpiece specifications. |
Check the proposed configuration against the robot manufacturer’s published specifications. Test the complete task with the actual or representative workpiece and tooling. |
15% |
| Integration engineering |
Ability to design and deliver the complete cell, including tooling, fixtures, controls, communications, and process sequencing. |
System architecture; electrical and pneumatic drawings; interface list; I/O map; software and sequence description; examples of comparable completed applications. |
Review a design walkthrough and ask the supplier to explain how faults, restarts, recipe changes, and handshakes with existing equipment are handled. |
15% |
| Safety engineering |
Risk assessment and safeguards for the robot application, tooling, workpiece, and surrounding cell. |
Application-specific risk assessment; safety-function list; safeguard layout; validation records; documentation identifying applicable standards and editions. |
Confirm that the assessment covers the complete installed application, not only the robot. Have safety functions and protective measures checked during commissioning by qualified personnel. |
15% |
| Application validation |
Whether the proposed process can meet agreed quality, throughput, and reliability requirements. |
Acceptance-test plan; measurable pass/fail criteria; sample cycle-time data; process capability or inspection results where relevant; test conditions and limitations. |
Run a witnessed factory or site acceptance test using representative parts, tooling, and operating conditions. Record results against the agreed criteria. |
12% |
| Controls and software |
Compatibility with required PLCs, sensors, vision systems, field networks, data collection, and operator interfaces. |
Supported interface list; network and I/O architecture; software scope; backups; user and maintenance documentation; change-control procedure. |
Demonstrate the required signals and recovery behavior on a test setup or during acceptance testing. Clarify software ownership, access, and update responsibilities. |
10% |
| Commissioning and project delivery |
Project planning, installation scope, commissioning method, training, and handover responsibilities. |
Project schedule; scope and exclusions; responsibility matrix; installation checklist; commissioning plan; operator and maintenance training plan. |
Check that milestones, site-readiness requirements, acceptance criteria, and change-order processes are written into the project documentation. |
10% |
| Service and spare parts |
Local technical support, escalation route, spare-parts planning, and response commitments. |
Support coverage and hours; service-level terms; escalation contacts by role; recommended spare-parts list; warranty terms; repair and replacement process. |
Verify service commitments in writing and confirm which party handles robot, end-effector, vision, safety, and third-party equipment issues. |
10% |
| Supplier capability and quality |
Relevant engineering experience, project controls, documentation quality, and repeatable build and test processes. |
Redacted project references; engineering and quality procedures; inspection records; project organization; sample manuals and drawings. |
Speak with references for comparable applications, with permission. Review whether delivered documentation matches the proposed scope and local operating requirements. |
8% |
| Commercial and lifecycle cost |
Total cost beyond the robot purchase, including integration, tooling, installation, training, maintenance, and future changes. |
Itemized quotation; inclusions and exclusions; warranty; consumables and maintenance assumptions; change pricing; expected lifecycle cost assumptions. |
Compare quotations on the same scope and acceptance criteria. Separate one-time costs from recurring costs and document assumptions that could affect the total. |
5% |